2592x
001152
2019-11-12

Funke Media Office, Essen, Germany

The Funke Media Group, headquartered in Essen, Germany, initiated a new corporate headquarters construction project to accommodate around 1,000 employees at an important traffic junction in the city center. The three-building complex includes a total area of 398,265 ft² in addition to a 300-car parking garage.

For this award-winning architectural project, FCP was hired as the general contractor in a joint venture with AllesWirdGut Architektur. Construction began at the end of 2015, with completion in January 2019.

The Funke Media office includes an elongated double structure with a connecting bridge tunnel as well as a circular media tower with a supplementary steel structure and media facade. The buildings, with 6 to 7 aboveground stories, are designed as framed structures consisting of reinforced concrete flat slabs, columns, and shear walls in the access zones.

The unique architectural design elements are the V-shaped columns on the double structure ground floor. The SB3 quality V-shaped columns give the impression of a "floating" monolithic structure on this open story. For this design, the V-shaped columns intersect the building’s orthogonal support beams, which required massive steel components. Additionally, the columns’ reinforcement, their connections, and reaching concrete design strength class C50/60 were extremely complex challenges. To tackle this issue, the building company created a preliminary design of the V-shaped columns to determine potential issues (formwork, reinforcement installation, concrete compaction, and so on) and create a design plan for optimal results.

A shallow subway structure (tunnel and emergency exit) located under the building posed another technical challenge. A combined pile-raft foundation (KPP) was needed to meet the allowable soil pressure and more importantly, to minimize building settlement. To limit settlement, the 47-inch-diameter bored piles along the subway structure (soil covering only 3 ft from the lower edge of the floor slab) were extended to a rigid soil layer depth to serve as a "rigid abutment". Regular (nightly) survey control work in the subway tunnel monitored settlement calculations. To prevent vibration, measures were taken close to the emergency exit.

The foundation, as well as the complexity of the supporting structure, were particular challenges in both the planning and design phases. This required advanced engineering knowledge to minimize construction time and costs.

Location Friedrichstrasse 34-38
45128 Essen


Project Specifications

Model data

Number of Nodes 2360
Number of Lines 3347
Number of Members 783
Number of Surfaces 580
Number of Load Cases 69
Number of Load Combinations 15
Number of Result Combinations 25
Dimensions 412.24 x 200.6 x 195.28 feet
Program Version 5.21.01

Do you have any questions?