[EN] FAQ 004209 | A PC is used by several users. Each user wants to use a different ...

Question:
A PC is used by several users. Each user wants to use a different file structure in Project Manager. How can this be done?

Answer:
The directory tree in Project Manager is managed in the PRO.DLP file. This is located in folder C:\ProgramData\Dlubal\Global\Project Manager by default. You can check the directory paths of Project Manager in the "Program Options" dialog box (click Project Manager menu "Edit → Program Options"); see also Image 01. This database file is available to all users. If each user should use a different project structure, you can create a PRO.DLP for each user (for example, PRO_User1.DLP, PRO_User2.DLP). The relevant database file must then be set by the respective user in the program options after each change of a user. This is also demonstrated in the video.