安联足球场(Allianz Arena)外墙,德国慕尼黑

客户项目

结构设计 Facade
IPL Ingenieurplanung Leichtbau GmbH
formTL ingenieure für tragwerk und leichtbau
Radolfzell, Germany
www.form-tl.de

Solid Construction
Arup Associates
London, UK
www.arupassociates.com
建筑师 Herzog & de Meuron
Basel, Switzerland
www.herzogdemeuron.com
建造 General Contractor
Alpine Bau Deutschland AG
Eching, Germany

General Planner
HVB Immobilien AG
Munich, Germany
www.hvbimmobilien.com
投资商 Allianz Arena - München Stadion GmbH
Munich, Germany
allianz-arena.com

Length: 227 m | Width: 258 m | Height: 50 m | Circumference: 840 m
Number of Nodes: 21,572 | Members: 18,672 | Materials: 2 | Cross‑Sections: 36

Allianz Arena is a football stadium in Munich, Germany, which hosted the opening match of the 2006 FIFA World Cup. The stadium became a new landmark of the city. The translucent exterior facade emits light in various colors and thus makes the whole arena very special.

Engineers faced the task to turn the architectural vision of the architects of Herzog & de Meuron from Switzerland into reality. Structural engineering and dimensioning posed special requirements on the engineers.

Structure and Dimensions

The wall facade of Allianz Arena in Munich is a steel structure covered by foil cushions. It consists of a spatially curved structure that encloses the external side of the solid structure in an elliptical shape, with a height of +12.40 m to 43.75 m above the playing field level. The ellipsis radius is 130 m and 115 m, and the circumference is about 810 m.

The central part of the steel structure is a rhombic grid. The grid is mainly supported by rigid brackets arranged radially on the solid structure or on the primary steel, which are pin-joined to the grid.

The covering of the ventilated facade consists of 768 pneumatic ETFE cushions in the shape of rhomboids that are connected to rectangular tubes. Also, 96 cushions form a ring around the whole stadium. Eight ring cushions build up the wall facade. Each cushion is connected to two horizontal and two diagonal frame beams. The seamless design of the structural grid allows for effective detailing of the cushions.

Structural Analysis

When developing the structure, the aim was to minimize the loads due to restraints in the steel structure. The main causes of the effects due to restraint are the temperature differences in the steel structure as well as the movement of the structure that was built in eight independent construction stages.

In order to reduce the effects due to restraint, normal force hinges were used in almost all crossing points of the steel grid. Deformation of the normal force hinge was limited to avoid damaging the cushions in the case of the substructure deformation. Since this was considered in the designed load combinations, some of the hinges took the effects and rigid connections were generated at the corresponding locations.

For the representation of complex structural behavior, an iterative calculation according to the second-order analysis was performed, taking into account the entire structure form without stresses.

With kind support of
Christian Würfl, Gerhard Fessler
Project managers of Allianz Arena by IPL GmbH

Program Used for Structural Analysis

联系我们

联系 Dlubal

如果您有任何关于我们产品的问题或者建议,请联系我们的技术支持或者搜索我们的问题和解答 (FAQs)。

+49 9673 9203 0

(可要求接中文热线)

info@dlubal.com

新闻简报

订阅相关新闻简讯,并获取有关实用的建议、计划举办的活动以及独家促销和优惠卷的信息。