Why is the 'Earth covering (permanent)' option greyed out in Window 1.4 of the FOUNDATION Pro add‑on module?

Answer

If you have selected neither the direct calculation of the ground failure design according to EN 1997‑1 Annex D nor the design of the safety against sliding, it is not necessary to enter a soil profile. You can enter the earth covering as a load later.