2020-11-06

This challenging project includes the new boiler house for Melamin d.d. Kočevje, equipped with a fully functional 9.8 MW biomass plant. The complicated installation was carried out next to an old steam boiler that was still in operation. The model shows the deformation shape of the structure in RFEM. For more information, see ag-i.si. Model and deformation shape © AG-inženiring.


(0)
0 out of 5 stars
5 star 0
4 star 0
3 star 0
2 star 0
1 star 0

Steel Structure of Boiler House for Biomass Plant

No Download Possible Customer Project / View Only
Number of Nodes 266
Number of Lines 555
Number of Members 532
Number of Load Cases 9
Number of Load Combinations 94
Number of Result Combinations 2
Total Weight 50.517 t
Dimensions (Metric) 22.267 x 22.228 x 15.715 m
Dimensions (Imperial) 73.05 x 72.93 x 51.56 feet
Program Version 4.10.19