Model of a temporary staircase leading from the Monbijou Bridge to the gasworks site in Bern, Switzerland. The temporary steel structure provides a safe pedestrian connection during the construction stage. The model includes the supporting elements of the staircase, including handrails and landings. It serves as a reference project for modeling temporary access structures using RFEM and RSTAB. This customer project is not available for download.


(0)
0 out of 5 stars
5 star 0
4 star 0
3 star 0
2 star 0
1 star 0

Temporary Staircase from Monbijou Bridge to Gasworks Site

No Download Possible Customer Project / View Only
Number of Nodes 256
Number of Lines 507
Number of Members 502
Number of Surfaces 0
Number of Solids 0
Number of Load Cases 14
Number of Load Combinations 515
Number of Result Combinations 2
Total Weight 17.681 t
Dimensions (Metric) 8.300 x 20.200 x 5.440 m
Dimensions (Imperial) 27.23 x 66.27 x 17.85 feet
Report This 3D Model