Due to the large number of beams with a maximum span of 30 meters, ensuring stability during assembly was of key importance. From an efficient and practical point of view, a modular lifting method with crane installation of entire structural components was chosen for the assembly. RFEM 6 was used to check the structural model, ensuring a convenient and cost-efficient construction process.
The structural engineers used the Construction Stages add-on to define each construction stage in order to ensure safety throughout the entire construction process. They also used the Steel Design add-on to assess the load-bearing capacity of the steel components at each stage, thereby ensuring structural safety during construction.
| Location | China |