sixpack Lift Station in Filzmoos, Austria
Customer Project
A modern 6-seater chairlift called sixpack Mooslehen opened in Filzmoos, Austria on December 17, 2021, right on time for the start of the ski season. The construction time for the entire project was only six months. The company m3-ZT, an Austrian customer of Dlubal, was responsible for the structural analysis, using the FEA program RFEM.
Project Management | the Moosleitner family |
Structural Design |
m3-ZT GmbH 5342 Abersee Austria
www.m3-zt.at |
Model Parameters
Model
The new valley station was built at 3,468 ft, the new mountain station at 4,452 ft. The aerial lift climbs exactly 300 m (984 ft) and its 43 chairlifts take up to 2,000 people per hour to the top of the mountain.
Construction of the Valley Station
The station's main supporting structure consists almost entirely of grade S 235 steel. S 355 steel was used only for the bracings and some slender columns. A total of about 87 tons of steel were used. The station's main dimensions are L x W x H = 141 x 92 x 33 ft. The facade, which includes large glass surfaces, was clad with timber. The maximum snow load was set at 1,080 lb per 10.8 square feet.
The new elevated passenger ropeway meets modern standards and takes skiers up the mountain quickly and comfortably.
Project Location
Filzmoos 114Keywords
Write Comment...
Write Comment...
Contact Us
Do you have any further questions or need advice? Contact us via phone, email, chat or forum or search the FAQ page, available 24/7.

Parametrization of Rolled Cross-Sections
Rolled sections, the most common cross‑section type in RFEM and RSTAB, can also have user‑defined parameters.
- How do I apply wind load on members of open structures?
- I do not want to design a cross-section in the RF‑/STEEL EC3 add-on module. Can I quickly remove this cross-section from the selection?
- I have a roof structure resting on a steel column that runs to the foundations. The column runs through a perimeter wall that supports the false ceiling. A considerable part of the load from the roof is transferred to the wall. I want the steel column to carry all the vertical loads from the roof. How can I do it?